Business Mould Division Automotive


CONSTRUCTION
CAVITY
STEEL MATERIAL
PLASTIC MATERIAL
GUARANTEE SHOT
DELIVERY
COLD RUNNER/RED RUNNER
1
MOULD BASE: KP4
CAVITY: KP4
OTHER
 
300,000 SHOTS
80 DAYS




ITEM
CAVITY
STEEL MATERIAL
PLASTIC MATERIAL
GUARANTEE SHOT
DELIVERY
REMARKS
MX-AIM
C x 1
ASSAB-718 & MOULD-MAX
PA6B + GF 30%
800,000~1,000,000 SHOTS
MASS PRODUCTION TYPE : 
8~10 WEEKS
PROTO TYPE : 4~6 WEEKS
CYCLE TIME : 45 ~ 50




CONSTRUCTION
CAVITY
STEEL MATERIAL
PLASTIC MATERIAL
GUARANTEE SHOT
DELIVERY
REMARKS
COLD RUNNER/RED RUNNER
1
MOULD BASE: KP-4
CAVITY
OTHER
P.P.
100,000 SHOTS
8 MONTHS to T1
FULL WORKS of CAVITY PART 
ON UPPER MOULD PART




CONSTRUCTION
CAVITY
STEEL MATERIAL
PLASTIC MATERIAL
GUARANTEE SHOT
DELIVERY
REMARKS
HOT RUNNER 
/OPEN GATE 4 POINT
1
M/R: KP-1
CORE: KP-1
P.P.
200,000 SHOTS
240 DAYS - 270 DAYS
SURFACE SIDES TEXTURED 
TYPE




CONSTRUCTION
CAVITY
STEEL MATERIAL
PLASTIC MATERIAL
GUARANTEE SHOT
DELIVERY
REMARKS
COLD RUNNER/
RED RUNNER(OPEN GATE)
1
MOULD BASE: KP-4M
CAVITY
OTHER
P.P. or ABS
300,000 SHOTS
2 MONTH to T1
3 SIDES TEXTURED




CONSTRUCTION
CAVITY
STEEL MATERIAL
PLASTIC MATERIAL
GUARANTEE SHOT
DELIVERY
REMARKS
COLD RUNNER(OP)/
HOT RUNNER,
HOUSING-OPEN GATE(2)
LENSE-VALVE GATE
1
MOULD BASE: KP-4M
LENS-ACRYLIC 
HOUSING-P.P.
LENS-300,000 S  
HOUSING-300,000 S
LENS-3MONTH to T1  
HOUSING-2MONTH to T1
LENSE-MULTI INJECTION
-WELDING(JIG)
HOUSING-NORMAL
-WELDING(JIG)




CONSTRUCTION
CAVITY
STEEL MATERIAL
PLASTIC MATERIAL
GUARANTEE SHOT
DELIVERY
REMARKS
COLD RUNNER/RED RUNNER
1
MOULD BASE: KP-4 or 
ALUMINUM CORE
CAVITY
OTHER
P.P.
300,000 SHOTS
60 DAYS
FRONT AMBO
TEXTURED(3 SIDES)




CONSTRUCTION
CAVITY
STEEL MATERIAL
PLASTIC MATERIAL
GUARANTEE SHOT
DELIVERY
COLD RUNNER/HOT RUNNER
1
MOULD BASE: KP4M
CAVITY: KP4M
OTHER
P.P.+GLASS 10-15%
300,000 SHOTS
55DAYS